Advertisement 1

TC Energy 'confident' it will complete $14.5-billion Coastal GasLink pipeline by year's end

Costs have more than doubled on the 670-kilometre natural gas pipeline and could increase up to a further $1.2 billion if construction is not completed this year.

Article content

Despite construction challenges and ballooning costs on the Coastal GasLink pipeline that contributed to a $1.4 billion fourth-quarter loss reported Tuesday, TC Energy says it’s on track to complete construction this year on the project in northern B.C.

Costs have more than doubled on the 670-kilometre natural gas pipeline to $14.5 billion and could increase up to a further $1.2 billion if construction is not completed this year.

Advertisement 2
Story continues below
Article content
Article content

The company says it will have a better idea by the summer whether it will need to push construction into 2024. While 84 per cent of construction is complete, there are some remaining challenging areas such as river crossings that can only be undertaken during the winter months, Bevin Wirzba, TC Energy’s  executive vice-president of strategy and corporate development, said Tuesday.

“We . . . are confident that we’ve incorporated not only cost but schedule risks into our execution plan to deliver the mechanical completion this year,” said Wirzba.

“That said, it’s a linear project with some very challenging activities. So, we made an allowance in the event that we’re not able to achieve the scope that we have planned this year . . . and  there could be activities that extend into ‘24 and ‘25,” he said.

The pipeline will transport gas from northeast B.C. to LNG Canada’s $18 billion export plant being built near Kitimat on the north-central coast. The liquefied natural gas plant will compress gas to be loaded onto ships that will open up more efficient and faster overseas access to markets in Asia.

Article content
Advertisement 3
Story continues below
Article content

RCMP said equipment damage totalling millions of dollars was done by a group that attacked Coastal GasLink workers in northern B.C. after midnight on Feb. 17. The extent of the damage was revealed with sunrise Thursday.
RCMP said equipment damage totalling millions of dollars was done by a group that attacked Coastal GasLink workers in northern B.C. after midnight on Feb. 17. The extent of the damage was revealed with sunrise Thursday. PNG

The controversial pipeline has been hit by attacks on construction sites and blockades and recently came under scrutiny by some hereditary chiefs and environmental groups for alleged harm to fish habitat from construction at river crossings.

Government agencies with regulatory oversight such as the B.C. Oil and Gas Commission and the federal department of Fisheries and Oceans have not found any compliances or harms to the environment on the river crossings.

But the B.C. Environmental Assessment Office, which also has oversight of the construction project, has fined the company three times for a total of $455,000 for erosion and sediment control problems. The EAO has said there have been recent improvements.

After the company’s financial results were released Tuesday, some Wet’suwet’en hereditary chiefs said the massive cost overruns and ongoing delays to construction — while continuing to violate Wet’suwet’en rights and title — also raised new doubts over the commercial viability of the project.

“The magnitude of how much the project went up in cost should tell the world how dangerous it is,” said Wet’suwet’en hereditary chief Na’moks, also known as John Risdale. “TC Energy investors and those who support it should also know the economic risk that comes with it.”

Advertisement 4
Story continues below
Article content

The nascent liquefied natural gas (LNG) export industry has support from some First Nations, including the Haisla in Kitimat. Elected councils of 20 First Nations along the pipeline route have signed community and project agreements with the company.

Despite the significant loss, TC Energy reported it is increasing its dividend to shareholders, noted its revenues continue to increase and it has new projects coming on stream that will put it in good financial position.

LNG Canada is also examining whether it will build a second phase to its project in Kitimat and Wirzba said Tuesday TC Energy could supply additional gas by adding six compressor stations on the pipeline.

He said additional pipeline capacity could also potentially supply the Haisla-led Cedar LNG project that is working through an environmental assessment.

ghoekstra@postmedia.com

twitter.com/gordon_hoekstra

Recommended from Editorial
  1. LNG Canada site construction activities in Kitimat in September 2022.
    Rising costs raise doubts about future of B.C. LNG
  2. Kitimat on B.C.'s north-central coast, the terminus for Coastal GasLink's pipeline route to a liquefied natural gas project.
    Coastal GasLink in hot water over pipeline environmental violations

Support our journalism: Our in-depth journalism is possible thanks to the support of our subscribers. For just $3.50 per week, you can get unlimited, ad-lite access to The Vancouver Sun, The Province, National Post and 13 other Canadian news sites. Support us by subscribing today: The Vancouver Sun | The Province.

Article content
Comments
You must be logged in to join the discussion or read more comments.
Join the Conversation

Postmedia is committed to maintaining a lively but civil forum for discussion. Please keep comments relevant and respectful. Comments may take up to an hour to appear on the site. You will receive an email if there is a reply to your comment, an update to a thread you follow or if a user you follow comments. Visit our Community Guidelines for more information.

Latest National Stories
    This Week in Flyers